QUESTION 71
Company A acquires company B, which leads to a two-year program to integrate the processes and systems.
Company B uses a different project management process, and the company’s staff is unhappy about the acquisition. As a result, company B’s project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?

 
 
 
 

QUESTION 72
You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this scenario?

 
 
 
 

QUESTION 73
What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?

 
 
 
 

QUESTION 74
You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?

 
 
 
 

QUESTION 75
You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

 
 
 
 

QUESTION 76
You are the program manager of the GHY Program. Your program team has identified a risk dealing with the materials you will be using in the program. It is possible that if the materials are not installed properly they will cause serious damage in future phases of the program. Your team has recommended additional training and a consultant to help the team members install the material accurately to reduce the likelihood of the risk event. You agree and the team executes the risk response. What type of risk response have you implemented in this situation?

 
 
 
 

QUESTION 77
Wan is the program manager for his organization. He has been hearing reports that some project team members are complaining about the number of hours they’re required to work on the program’s projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

 
 
 
 

QUESTION 78
An organization supports both programs and projects for various industries. What is a portfolio?

 
 
 
 

QUESTION 79
Which of the following shows the ratio between a task’s budgeted and actual costs?

 
 
 
 

QUESTION 80
An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However, the business team does not report to the IT program manager, and only two business team resources with the appropriate skills are available to complete the required program tasks.
To address this issue, what should the IT program manager do next?

 
 
 
 

QUESTION 81
Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction.
These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?

 
 
 
 

QUESTION 82
Which one of the following is the best example of transference?

 
 
 
 

QUESTION 83
Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?

 
 
 
 

QUESTION 84
You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

 
 
 
 

QUESTION 85
Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances.
Mary Anne has decided, however, that her program needs to be terminated. Which one of the following is a likely reason why the project should be terminated?

 
 
 
 

QUESTION 86
Which of the following program process outputs includes causes of variances from the program management plan, corrective actions taken and their outcomes, risk mitigations, and other information of value to management and stakeholders of future programs?

 
 
 
 

QUESTION 87
You are the program manager for your program and are creating a communications management plan.
Management wants you to address the type of communications based on the number of communication channels you’ll have within the program. Currently there are 345 stakeholders in your program but next week you’ll have 387 stakeholders. How many more communication channels will you have next week in your program?

 
 
 
 

QUESTION 88
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk.
What should the program manager do to monitor and control the supplier?

 
 
 
 

QUESTION 89
Which one of the following is not considered one of the three components of the Iron Triangle?

 
 
 
 

QUESTION 90
You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time.
What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?

 
 
 
 

Prerequisites

To qualify for the PMI PgMP certificate, you need to meet certain educational and experience requirements. These include a secondary degree (this can be a high school diploma, an associate’s degree, or their global equivalent); 48 months of work experience in management or the PMP certification; 84 months of work experience in program management over the past 15 years. Alternatively, you can still qualify if you have the following: a 4-year degree; 48 months of work experience in project management or the PMP certificate; 48 months of experience in project management within the last 15 years.

The Panel Review

The first evaluation begins after selecting your application and payment for all necessary certifications. A panel of volunteer PgMP certified program managers assess your professional experience based on your responses in the Program Management Experience Summaries provided on the application form.

In this evaluation, all the information and credentials you stated in your application when applying for the PgMP exam are extensively reviewed.

 

Accurate & Verified New PgMP Answers As Experienced in the Actual Test!: https://www.dumpleader.com/PgMP_exam.html

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below