QUESTION 25
What two municipal plans are required to define a new civil infrastructure project?

 
 
 
 

QUESTION 26
A gas fireplace has been installed by the general contractor’s sub-trade. After numerous repair attempts, it is still not operating properly. How should the owner correct the problem?

 
 
 
 

QUESTION 27
What material property is measured by a sieve analysis?

 
 
 
 

QUESTION 28
A civil engineering technologist needs to recommend a foundation design for a commercial building. The borehole logs identify unsuitable bearing soils beneath the proposed floor elevation to a depth of 4 m and shallow bedrock at 5 m. Which of the following types of design should the technologist recommend?

 
 
 
 

QUESTION 29
Why would an owner require COR certification from a contractor?

 
 
 
 

QUESTION 30
Which of the following images shows the appropriate tool to measure the slump of concrete?

 
 
 
 

QUESTION 31
A subcontractor is completing surface rehabilitation in a mature community. What are the minimum requirements for quality that must be met?

 
 
 
 

QUESTION 32
Which of the following tests are required as part of soil grain size analysis?

 
 
 
 

QUESTION 33
What personal protective equipment is most important when surveying near active traffic?

 
 
 
 

QUESTION 34
A surveyor is laying out the invert elevations of a storm sewer. Centre elevation is 10 m, storm pipe outside diameter is 1 m, and storm sewer pipe wall thickness is 0.05 m. What is the storm sewer invert elevation in the diagram below?

 
 
 
 

QUESTION 35
A civil engineering technologist works for a contractor. An engineer notifies him that the depth of concrete pilings needs to be increased. What is the first thing the civil engineering technologist should do?

 
 
 
 

QUESTION 36
What should a contract administrator do when the contractor is falling behind schedule?

 
 
 
 

QUESTION 37
A contractor is using a compactor on a hot and dry day and quickly compacts a dry 300 mm thickness of sub- base without adding water. The soil is near optimum moisture. A civil engineering technologist completes compaction tests and finds that specifications have not been achieved. What should be done?

 
 
 
 

QUESTION 38
What documents must a contractor submit as part of a project to consultants for review?

 
 
 
 

QUESTION 39
The k-value in a vertical curve design defines the horizontal distance required to make a 1% change in the gradient. Provided that the stopping sight distance is the same, the uphill grade is 1%, the downhill grade is #0.
5%, and the design speed is 90 km/h, what is the length of the vertical curve?

 
 
 
 

QUESTION 40
Based on the diagram below, what is the percentage slope between D1 and C2 if the grid is 10 m × 10 m?

 
 
 
 

QUESTION 41
Which of the following should be done as part of project status report preparation?

 
 
 
 

QUESTION 42
A contractor fails to make the necessary repairs on the deficiency list within the specified timeline and refuses to return to the site. How should the owner proceed in this situation?

 
 
 
 

QUESTION 43
Whatto determine the compressive strength of concrete?

 
 
 
 

QUESTION 44
What is the most important information a civil engineering technologist should be familiar with before stepping onsite during site inspection?

 
 
 
 

Full Civil-Engineering-Technology Practice Test and 112 unique questions with explanations waiting just for you, get it now: https://www.dumpleader.com/Civil-Engineering-Technology_exam.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below