NEW QUESTION 53
Theoretically construct a summary activity for activities 2001 through 2004. Using the “normal” schedule, what is the cost of the hammock?

 
 
 
 

NEW QUESTION 54
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

 
 
 
 

NEW QUESTION 55
What is the workweek period for this project?

 
 
 
 

NEW QUESTION 56
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

 
 
 
 

NEW QUESTION 57
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

 
 
 
 

NEW QUESTION 58
What method offers the best chance of the schedule being used effectively to implement the project in the field?

 
 
 
 

NEW QUESTION 59
Each of the following accurately describes total float in a schedule EXCEPT:

 
 
 
 

NEW QUESTION 60
Which of the following project planning situations is the most frequent contributor to cost overruns?

 
 
 
 

NEW QUESTION 61
Which of the following is NOT true?

 
 
 
 

NEW QUESTION 62
At a minimum, periodic reporting must be done at what interval?

 
 
 
 

NEW QUESTION 63
Which statement is true?

 
 
 
 

NEW QUESTION 64
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

 
 
 
 

NEW QUESTION 65
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

 
 
 
 

NEW QUESTION 66
How could the structural steel drawing delay have been prevented?

 
 
 
 

NEW QUESTION 67
Total float is defined as the amount of time an activity can be delayed without impacting

 
 
 
 

NEW QUESTION 68
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor’s baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

 
 
 
 

NEW QUESTION 69
What is the result of a forward pass calculation?

 
 
 
 

NEW QUESTION 70
What is the relationship depicted between Activity G and Activity H?

 
 
 
 

Use Real AACE International Achieve the AACE-PSP Dumps – 100% Exam Passing Guarantee: https://www.dumpleader.com/AACE-PSP_exam.html

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below