NEW QUESTION 17
A federated model has been created for a multidisciplinary project, but clashes are being reported in areas where coordination should already be resolved. Upon investigation, the BIM manager finds that some models were exported with outdated links and local coordinates.
What is the most appropriate next step before proceeding with coordination analysis?

 
 
 
 

NEW QUESTION 18
A client is seeking bids from a range of possible fabricators to determine which will win the contract to join the team.
What settings in Autodesk Forma allow a team to distribute files to a party that is not a project member?

 
 
 
 

NEW QUESTION 19
The BIM manager received a subcontractor’s 3D model containing specialty equipment to be integrated into the federated model. Upon review, they observe that:
Many elements lack consistent object styles and category assignments.
Some components are modelled with excessive detail, affecting performance.
Embedded data does not follow the project’s naming conventions outlined in the BEP.
What is the most appropriate next step when evaluating this geometry and content?

 
 
 
 

NEW QUESTION 20
The BIM manager is working on a mixed-use project in which consultants are on different platforms and delivery timelines. The client requires COBie-compliant data handover and weekly coordination uploads.
What is the best approach to ensure project-specific BIM processes are effectively implemented from the outset?

 
 
 
 

NEW QUESTION 21
A BIM manager is preparing to share a federated model package with an external cost estimator. The estimator only needs access to quantities and location-based metadata, but not design intent or proprietary elements from other teams.
What is the first step the BIM manager should take to ensure appropriate use and minimize data-related risk?

 
 
 
 

NEW QUESTION 22
An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client’s preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model’s compatibility with internal systems.
As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)

 
 
 
 
 

NEW QUESTION 23
A design team requests a focused coordination review between the Architectural and Structural published design models. They want to exclude all other trades from the clash matrix.
What should the BIM manager do to ensure only the Architectural and Structural models are included in clash detection?

 
 
 
 

NEW QUESTION 24
The BIM manager is coordinating a multi-building project in which each building must maintain a unique internal coordinate system but share a common origin point for site-wide references.
Which two actions are required to correctly manage the coordinate setup in this scenario? (Select two.)

 
 
 
 
 

NEW QUESTION 25
The BIM manager receives an external lighting CAD file to link into the Architectural model and realizes the link is not vertically or horizontally aligned.
What fix needs to happen to resolve this misalignment?

 
 
 
 

NEW QUESTION 26
What setting should be defined in the Family Template for Mechanical Equipment families intended for use in projects in specific countries?

 
 
 
 

NEW QUESTION 27
A firm-wide Revit template has an advanced setup of views preset on sheets. A renovation project has a linked as-built model with levels that do not align with levels from the model template.
What method should a BIM manager use to update the levels and create grids in sync with the resource model, without requiring extensive reworking of the preset sheets?

 
 
 
 

NEW QUESTION 28
The BIM Execution Plan (BEP) has just been completed for a new project. To ensure all multidisciplinary team members review and understand their roles and responsibilities, what is the most effective way to distribute the BEP before the project starts and ensure it remains accessible to everyone throughout the project?

 
 
 
 

NEW QUESTION 29
A BIM manager is preparing to onboard a group of subcontractors into Autodesk Forma for a large healthcare project. These subcontractors need access to a limited set of model files related only to interior partitions, but should not be able to view or modify structural, MEP, or scheduling content.
What two actions should the BIM manager take to manage data security in this scenario? (Select two.)

 
 
 
 
 

NEW QUESTION 30
Due to unpredictable material tariffs, a campus project anticipates possibly changing its structural framing system once pricing is finalized. This could affect floor-to-floor heights across several buildings.
What method would best ensure both initial and ongoing coordination of Levels and Grids across a large multidisciplinary Revit project?

 
 
 
 

NEW QUESTION 31
A campus project of several duplicated links of a building model has received an updated civil background, with revised GIS coordinates.
Drag and drop to indicate the correct order of steps the BIM manager should perform to revise the architectural model.

NEW QUESTION 32
During a model health check, a BIM manager notices that an international airport project’s models are 1 GB each. The team has not mentioned any issues, but they did miss a recent 50% Construction Documents deadline.
What should the BIM manager do?

 
 
 
 

NEW QUESTION 33
The project manager would like to verify Autodesk Forma folder permissions assigned to team members but is not familiar with cloud-sharing platforms to access this information.
How can the BIM manager generate the required information?

 
 
 
 

NEW QUESTION 34
Refer to the exhibit.

A client has provided the design team with a title block family and a Shared Parameters file that must be used as part of their standards. Those provided parameters must be applied both in the Project Information area as well as the title block.
When the design team is in the project model and attempts to fill in information into the title block parameters, a question mark appears. What is the likely cause of this?

 
 
 
 

NEW QUESTION 35
During a project onboarding meeting, the client provides their current BIM standards and templates to the BIM manager. The project will involve multiple consultants across different regions and is being delivered under a fast-track schedule with a high volume of design iterations. The client has also indicated that they plan to use a new collaboration platform not previously piloted on similar project types.
The BIM manager must evaluate whether the client’s materials are sufficient and aligned with digital-delivery expectations, collaboration goals, and coordination requirements.
Given these factors, which two of the client’s BIM resources must be prioritized for review to evaluate their ability to support digital delivery and coordination across regions, teams, and time constraints? (Select two.)

 
 
 
 
 

NEW QUESTION 36
A regional user group raised awareness about a third-party add-on tool that enables a team to establish thresholds for model warnings. In addition, it automates suppressing warnings deemed negligible to a specific project.
Which two data points should a BIM manager gather to build a business case to have the tool approved for use across the firm? (Select two.)

 
 
 
 
 

NEW QUESTION 37
A museum project anticipating generative iterations is being designed by a team working across multiple time zones under a tight schedule. The client hosts weekly meetings to review various facade options, document sustainability goals, and evaluate numerous energy analyses.
What project-specific training should the design technology team provide to prepare the team for client meetings and ensure successful project execution?

 
 
 
 

NEW QUESTION 38
The BIM manager is launching a civic center project with strict sustainability and lifecycle data goals. During early planning, each discipline proposes different modelling approaches, and there is concern that downstream data handoff may be inconsistent.
To establish BIM goals and uses that ensure alignment from design through operations, what should the BIM manager do first?
Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.

 
 
 
 

NEW QUESTION 39
A team member accidentally unpinned and dragged a linked CAD file, and it is no longer aligned according to the Shared Coordinates.
How can the BIM manager realign the linked CAD file in the Revit model?

 
 
 
 

Pass Your Autodesk Exam with BIM_MGT_101 Exam Dumps: https://www.dumpleader.com/BIM_MGT_101_exam.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below